Ethiopia’s Public-Private Partnership Legal Framework: A Practitioner’s Guide

Ethiopia’s Public-Private Partnership (PPP) framework has undergone a meaningful evolution. This shift reflects the practical realities of launching infrastructure projects. It also highlights the country’s ambition to attract private capital at scale. Two key laws anchor the governing legislation: Proclamation No. 1076/2018 and the 2023 Amendment. Together, they establish a comprehensive regime. This system balances procedural rigour with the flexibility needed to close complex deals.

The Policy Foundations

Four core objectives anchor the framework:

  • Promoting private sector participation in public infrastructure.
  • Ensuring transparency, fairness, and Value for Money (VfM) in procurement.
  • Improving the quality and reach of public services.
  • Maintaining macroeconomic stability by keeping public debt within manageable limits.

A proposal that cannot demonstrate VfM over traditional public procurement will not advance.

In terms of scope, the framework applies to all PPP projects undertaken by public bodies and public enterprises. The original exclusions oil, mines, minerals, airspace rights, and straightforward privatization of state assets remain in force. However, the 2023 Amendment introduced a significant new carve-out: public enterprises that conduct business activities with a private party, a foreign government, or a public enterprise of a foreign government now fall outside the framework’s scope. In practice, this creates a parallel pathway. However, the 2023 Amendment introduced a significant new carve-out: public enterprises that conduct business activities with a private party, a foreign government, or a public enterprise of a foreign government now fall outside the framework’s scope

The Institutional Architecture

The PPP Board, chaired by the Ministry of Finance, holds ultimate decision-making authority. Successfully navigating the Ethiopian PPP landscape requires understanding three primary institutional pillars, which operate in a clear hierarchy. Public enterprises can now develop joint ventures with private companies or foreign states. They do this by incorporating a separate vehicle. This approach completely bypasses the rigid procedural requirements of conventional PPP projects.

The PPP Directorate General (PPP DG), housed within the Ministry of Finance, functions as the Board’s technical secretariat. The Board approves the PPP pipeline and endorses feasibility studies. It also selects winning bidders and signs off on risk allocation changes. Additionally, two private sector members sit on the Board. This sends an important signal. It shows the legislature’s intent to keep commercial perspectives in the room.

The Contracting Authority is the public entity with statutory responsibility for the relevant infrastructure or service. It owns the project from conceptualisation through to contract administration and is the counterparty to the PPP agreement itself.

The Project Lifecycle

Identification and Preparation

Before any project moves to procurement, a detailed feasibility study must cover technical, financial, environmental, and social impact dimensions. The project must explicitly demonstrate Value for Money (VfM) against traditional public procurement.

The Ministry of Finance must approve the initial application before the contracting authority commissions a full analysis, functioning as an early-stage filter to protect public resources.

Procurement

The default procurement method is open bidding with pre-qualification: a qualification phase followed by a proposal phase open only to pre-qualified bidders, governed throughout by the principles of transparency, free competition, and equal treatment.

For technically complex projects where the contracting authority cannot fully specify the solution in advance, competitive dialogue and two-stage bidding are available. These modalities permit iterative engagement with the market before bidders lock in their final bids.

The most substantive procedural change introduced by the 2023 Amendment concerns direct negotiations. Under the original framework, direct negotiations were a narrow fall-back available only in cases of national security, single-source technology, or procurement failure. The Amendment transforms this into a genuine procurement pathway. The PPP Board may now endorse a project for direct negotiations where it determines this serves the public interest and ensures quick financing, including where the proposal originates through bilateral intergovernmental economic diplomacy or through direct contact with a foreign company.

To access this pathway, private parties must satisfy mandatory eligibility requirements: a certificate of incorporation accompanied by evidence of home-government support for the project; demonstrated financial and technical capacity, including prior delivery of at least two comparable projects; and evidence that the project promotes domestic investor participation, the use of local products, and the employment of Ethiopian nationals. This local content requirement which the PPP Directive encourages but does not mandate in competitive processes becomes compulsory in the direct negotiation context.

The framework also accommodates unsolicited proposals, allowing private parties to pitch projects outside the government’s pipeline, subject to transparency safeguards designed to prevent the originating company from gaining an unfair advantage in any subsequent procurement.

The PPP Agreement

Ethiopian law must govern all PPP agreements—a mandatory rule that applies regardless of the private party’s nationality or the jurisdiction of its lenders. The framework obligates the contracting authority to assist the private partner in securing land rights and site access, providing critical practical support for infrastructure-heavy projects.

The framework includes a stability clause protecting the private party against targeted legislative changes that materially alter the project’s financial equilibrium. Where such changes occur, the private party has the right to seek a rebalancing of the economic terms. This provision gives investors confidence that the government will not unilaterally reset the regulatory environment after financial close.

Private partners may grant security interests — mortgages and pledges — over project assets or shares in the project company to secure financing from lenders. Any change of control in the project company, including share transfers by the private party, requires prior approval from the contracting authority.

Dispute Resolution

The parties are free to choose their preferred dispute resolution mechanism, expressly including international arbitration. For foreign investors and project lenders, the ability to submit disputes to a neutral international forum is typically a non-negotiable condition of involvement, and the framework’s explicit recognition of this is commercially significant.

Conclusion

Ethiopia’s PPP framework reflects a legislature wrestling seriously with the tension between procedural safeguards and the practical need to move faster on infrastructure. The 2023 Amendment resolves that tension, at least partly, in favour of speed expanding the direct negotiation pathway, recognising intergovernmental economic diplomacy as a valid project origination mechanism, and carving out space for public enterprise joint ventures that operate outside the conventional PPP process.

For practitioners advising on Ethiopian infrastructure projects, the key questions are now less about whether they can structure a deal as a PPP and more about which pathway—open bidding, direct negotiation, or the new public enterprise exemption—is most appropriate for the specific transaction. Each carries different procedural obligations, different timelines, and different risk profiles. Getting that foundational analysis right is where effective legal advice in this space begins.